Septembre 2016 / Reuters

EDF struggles with long nuclear plant closures - Les Echos



PARIS, Sept 9 (Reuters) - ** Manufacturing irregularities in Areva's Creusot plant weigh heavily on EDF reactor outages. Fessenheim 2 restart delayed by several months to end March 2017. Was halted by regulator ASN mid-June following discovery of irregularities in steel of reactor vessel.

** EDF investigating 18 reactors following discovery of irregularities in steel. Eight have been controlled so far and received ASN green light, five others remain closed as checks are ongoing, (…)

> Voir la source


Thèmes
 Anomalies