31 May (NucNet) : Commercial operation of the Flamanville-3 EPR unit under construction in northern France could be further delayed because of the need for safety checks after flaws were discovered in the weldings of the reactor’s secondary circuit, reports in French media have said.
The unconfirmed reports quoted Thierry Charles, deputy director-general in charge of nuclear safety at the Institute for Radiation Protection and Nuclear Safety (IRSN), as saying operation of (...)