Plant Status of Fukushima Daini Nuclear Power Station (as of 11pm March 12th)



Please note this is a press release of the Japanese utility operating the Fukushima plant.

Press Release

[New Items are underlined]

Unit 1 (shut down at 2:48pm on March 11th)

▸ Reactor is shut down and reactor water level is stable.

▸ Offsite power is available.

▸ At 8:19am, there was an alarm indicating that one of the control rods was not properly inserted, however, at 10:43am the alarm was spontaneously called off. Other control rods has been confirmed that they are fully (…)