France’s Regulator Extends Deadline For EDF To Carry Out Bugey-5 Containment Checks



22 Nov (NucNet) : France’s nuclear regulator says it has extended the deadline for checks to be carried out by operator EDF on the Bugey-5 nuclear plant in eastern France.

The Autorité de Sureté Nucléaire (ASN) said the deadline extension did not have any safety implications and the 880-MW pressurised water reactor remains in cold shutdown.

The checks include pressure and leak tests of the unit’s safety containment. ASN said these tests have been delayed because EDF detected a (...)