London (Platts)—6 Dec 2016 1129 am EST/1629 GMT
* EDF to communicate schedule to RTE soon
* Dampierre-3, Gravelines-2 and -4, Tricastin-1, -2, and -3 fully tested
* Generic decision for two 1.45-GW units expected in December too
EDF will spread out through to the end of the year the restart of the reactors that have been fully checked and soon expected to obtain final clearance from French nuclear safety authority ASN, an EDF spokesman said Tuesday.
"We are now (...)