9 September 2017
La centrale définitivement fermée est en cours de démantèlement. Il n’y a pas de mouvement de combustible en cours et les groupes électrogènes sont disponibles pour assurer le secours du refroidissement du combustible.
Type : PWR - Puissance : 2 609 MWth - Première divergence : 1 / 1977 - ARRÊT DEFINITIF : 20 02 2012 -
Available in english only
Event Number: 52957
Facility: CRYSTAL RIVER - State: FL Unit: [3] - RX Type: [3] B&W-L-LP
Event Date: 09/09/2017 - Event Time: 11:09 [EDT]
Emergency Class: NON EMERGENCY 10 CFR Section:
Initial PWR : 0 % Current PWR : 0 %
Event Text
HURRICANE WARNING ISSUED AFFECTING SITE WITHIN 36 HOURS
Crystal River Unit 3 is currently undergoing decommissioning and is permanently shut down.
The licensee entered their adverse weather procedure EM-220D based on a Hurricane Warning affecting the site within 36 hours. All applicable sections of EM-220D are complete or in progress.
No fuel movement activities are in progress. All equipment including Emergency Diesel Generators (EDGS) is available to perform required spent fuel cooling.
The licensee will inform the NRC Region I Office.
https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2017/20170911en.html