By JAMES RISENFEB. 8, 2016
WASHINGTON — Time may finally be running out on the Mixed Oxide Fuel Fabrication Facility, a multibillion-dollar, over-budget federal project that has been hard to kill.
The Energy Department has already spent about $4.5 billion on the half-built plant near Aiken, S.C., designed to make commercial reactor fuel out of plutonium from nuclear bombs. New estimates place the ultimate cost of the facility at between $9.4 billion and $21 billion, and the (...)