Décembre 2007 / Platts

Finnish EPR : 2,5 years delays and overcosts for French Taxpayers



Platts, 28 December 2007

Olkiluoto-3 completion targeted for summer 2011

Olkiluoto-3 will be completed in "summer 2011," Finnish utility

Teollisuuden Voima Oy said. TVO said the Areva-Siemens consortium, which

had previously targeted 2011 after a two-year delay on the original

schedule, had informed it December 28 of the summer target.

TVO said the turbine building has reached roof-top level and that

some turbine components have arrived in Finland. Turbine generator (...)