By SAMMY FRETWELL and AVERY G. WILKS
sfretwell@thestate.com, awilks@thestate.com
September 04, 2017 7:05 PM
The doomed V.C. Summer nuclear project suffered from flawed construction plans, faulty designs, inadequate management of contractors, low worker morale and high turnover, according to a lengthy and long-secret report released Monday by S.C. Gov. Henry McMaster’s office.
The report, completed by the Bechtel Corp. about 18 months before the project was shut down in (...)