Flamanville supply chain ’needs oversight’
27 October 2008
Areva has been told to monitor its subcontractors more closely after it was discovered that one had supplied a pressure system part without properly following testing procedures.
https://www.world-nuclear-news.org/RS_Flamanville_supply_chain_needs_oversight_2710081.html
The parts in question are to be used to form the pressurizer of the water-cooled reactor under construction at Flamanville. The pressurizer is a main (...)