Septembre 2017 / Reuters

EDF’s 2018 target for starting Flamanville reactor is ’tight’ - regulator



Reuters Staff -

September 6, 2017 / 3:32 PM

* Major test of Flamanville safety systems due mid-2018

* Schedule for 2018 fuel loading and start-up is tight

* Grid connection planned May 2019, full capacity Nov 2019 (Adds IRSN official comments on testing and start-up timing)

By Geert De Clercq

PARIS, Sept 6 (Reuters) - French utility EDF’s schedule to start up its new EPR nuclear reactor in Flamanville, northern France, by the end of 2018 is tight, a top nuclear (...)

> Voir la source


Thèmes
 EPR  Flamanville