EDF Energy Says It Achieved All Key Goals For Hinkley Point C In 2017



16 Feb 2018 : UK-based EDF Energy has achieved all 2017 key goals set for the Hinkley Point C nuclear power station project under construction in Somerset, England, the company said in a statement.

EDF said 2017 saw the pouring of the first nuclear safety concrete for the underground service tunnels, the installation of three concrete batching plants, and the start of construction work on a temporary jetty.

By the end of 2017, there were nearly 3,000 people working on site, EDF (...)